A cold room can pass a factory acceptance test (FAT) and still fail to perform after installation. Factory testing can verify supplied components, workmanship, electrical functions and, where facilities permit, refrigeration operation. It cannot automatically prove that the completed room will hold its specified temperature under the site’s actual ambient conditions and product load.
The distinction matters when agreeing on acceptance criteria with a cold room factory. A useful FAT checklist identifies what will be tested before shipment, what evidence will be supplied and which checks must be repeated during site acceptance testing (SAT).
A cold room may arrive as panels, doors, an evaporator, a condensing unit and controls that are assembled only at the destination. If the entire system will not be assembled at the factory, describe the FAT as a component or subsystem inspection rather than a full room performance test.
The approved FAT plan should identify:
Agree whether inspection will be witnessed in person, remotely or through submitted records. A factory test report is more useful when it identifies the actual unit tested and the conditions under which the results were obtained.
Inspect panel dimensions and thickness against approved drawings, including openings, floor details and panel identification. Check for damaged facings, exposed insulation, distorted edges and defects that could prevent joints from closing properly. Verify that the supplied locking hardware, joint seals and installation materials match the design.
Where a representative assembly is included in the FAT, check panel alignment and joint fit. A visual inspection of separate panels cannot establish the airtightness of the completed enclosure. Any specified site leakage or thermal inspection should therefore remain on the SAT list.
For doors, check the clear opening, handing, frame dimensions, hinges, latches and gasket continuity. Open and close the door repeatedly to confirm that it operates without binding and that the seal makes consistent contact. Check the specified emergency release from inside the room and, where fitted, verify the operation of door heaters and heater controls. A door that closes under factory conditions may still need adjustment after the frame and floor are installed.
Review insulation-core and facing specifications against the purchase documents. If fire performance is required, request test or classification documents for the relevant panel construction and intended application; a material claim alone does not establish compliance for every assembled wall or site condition.
Check equipment nameplates and drawings against the approved schedule: compressor, evaporator, condenser or condensing unit, fans, valves, controls and refrigerant. Confirm that connection sizes and positions are compatible with the installation drawings. Inspect coils and pipework for damage, and check that service connections and components are accessible.
For a packaged unit such as the Spiral Condenser Unit, FAT documentation should identify the supplied configuration and electrical requirements. If remote alarms or phase-loss protection are specified, include functional checks rather than relying solely on the product description. A condensing-unit test does not verify the capacity of the complete cold room system.
Refrigerant circuit pressure and leak tests should follow the approved design, applicable safety requirements and component pressure ratings. Record the test medium, pressure, duration, acceptance criterion and result. Test pressure must not exceed the allowable limits of the components under test. Never use oxygen for pressure testing refrigeration pipework, and do not treat a vacuum test as a substitute for an appropriately specified pressure and leak test.
Compare the control panel with the approved schematic and equipment schedule. Inspect terminal identification, cable routing, protective devices, enclosure condition, protective bonding and provision for isolating the supply. Verify that the nameplate supply matches the purchase specification, including voltage, frequency and phase.
Electrical tests must be appropriate to the equipment and performed safely by competent personnel. The agreed procedure should identify which protective-bonding, insulation-resistance or dielectric checks apply and how sensitive electronics are protected during testing. Record measured values and the specified acceptance limits; a generic “electrical test passed” statement provides little traceability.
Function-test the controls that can safely be exercised at the factory:
Document any simulated test and its limits. For example, triggering an alarm input can verify the controller’s response without proving that the field sensor and its installed wiring will operate correctly at site.
If a complete or representative refrigeration system is available for a run test, define the conditions before comparing results with the specification. Record supply voltage, ambient and operating temperatures, pressure readings where appropriate, test duration, sensor locations and the operating state during measurement. Use instruments with calibration traceable to an appropriate standard, and identify them in the report.
A room temperature reading alone does not establish cooling capacity. Capacity depends on the test conditions and measurement method; a pull-down test in an empty enclosure also differs from operation with warm product, door openings and infiltration. If a capacity figure is an acceptance requirement, specify the rating conditions and an agreed measurement method in advance. Do not compare capacity values quoted at different evaporating or condensing conditions as though they were equivalent.
Where a full-load test cannot be reproduced, record the limitation and agree on the remaining commissioning checks. Site testing should address the installed enclosure, refrigeration connections, defrost drainage, controls and performance under the agreed operating conditions.
List the applicable regulations and standards in the contract by edition and jurisdiction. Depending on the installation and equipment scope, relevant references may include the ISO 5149 or EN 378 refrigeration safety series and IEC 60204-1 for electrical equipment of machinery. Applicability depends on the product, installation and local requirements; citing a standard does not by itself demonstrate conformity.
For any required certificate or test report, check the issuing body, model or product range, standard and edition, validity and scope. A component certificate does not automatically cover the assembled cold room, and a quality-management certificate is not a product safety approval. Where a declaration of conformity is required, ensure that it corresponds to the equipment and legal requirements for its destination.
The final package should include the approved test procedure, completed checklists, measured results, instrument identification, equipment identification, relevant drawings and certificates, and a list of deviations. Each nonconformity should have an owner, corrective action, verification method and closure status. If shipment is permitted with an open item, record the approval and the required site action.
Before release, inspect preservation and packing: protect coil fins and electrical panels, secure loose components, cap pipe connections as specified and label packages against the packing list. The FAT sign-off should state exactly what passed, what was not tested and what remains for site acceptance. That boundary is essential evidence when the delivered system is assembled and commissioned.